LIVE Gold Prices $  | E-Mail Subscriptions | Update GoldSeek | GoldSeek Radio 

Commentary : Gold Review : Markets : News Wire : Quotes : Silver : Stocks - Main Page 

 GoldSeek.com >> News >> Story  Disclaimer 
 
Latest Headlines

GoldSeek.com to Launch New Website
By: GoldSeek.com

Is Gold Price Action Warning Of Imminent Monetary Collapse Part 2?
By: Hubert Moolman

Gold and Silver Are Just Getting Started
By: Frank Holmes, US Funds

Silver Makes High Wave Candle at Target – Here’s What to Expect…
By: Clive Maund

Gold Blows Through Upside Resistance - The Chase Is On
By: Avi Gilburt

U.S. Mint To Reduce Gold & Silver Eagle Production Over The Next 12-18 Months
By: Steve St. Angelo, SRSrocco Report

Gold's sharp rise throws Financial Times into an erroneous sulk
By: Chris Powell, GATA

Precious Metals Update Video: Gold's unusual strength
By: Ira Epstein

Asian Metals Market Update: July-29-2020
By: Chintan Karnani, Insignia Consultants

Gold's rise is a 'mystery' because journalism always fails to pursue it
By: Chris Powell, GATA

 
Search

GoldSeek Web

 
Positive Prefeasibility Study For Caspiche


-- Posted Monday, 30 January 2012 | | Disqus

Unlocking Value for Shareholders

Exeter Resource Corporation is a Canadian public company listed on the TSX and NYSE Amex exchanges. Our focus is the discovery, evaluation and development of gold deposits in the Maricunga district in Chile.

Exeter's 100% owned Caspiche Project in Chile (with a 3% Net Smelter Royalty to Anglo American Chile Limitada) is a gold-copper porphyry system, a type of deposit common to many of the world's largest open pit gold-copper mines. It is located in the prolific Maricunga mineral belt which is currently undergoing massive expansion and investment in mineral projects from some of the worlds largest gold miners. The project is located 15 kilometres (8 miles) south of Kinross Gold's operating Refugio mine (+9 million ounce gold reserve), and 10 kilometres (6 miles) north of the very large Cerro Casale gold-copper deposit (26 million ounce gold reserve), owned by Kinross Gold (25%)and Barrick Gold (75%).

The Pre-feasibilty study used proven and probable mining reserves in the development of the mine plan and financial evaluation (based on measured and indicated resources). Total proven and probable ore reserves, generated from an updated resource estimate for the Super Pit are 1.091 billion tonnes containing 19.3 million ounces gold, 4.62 billion pounds copper, 41.5 million ounces silver. This represents on of the largest mineral endowments for any deposit to be held by a junior explorer. Further its location within a developed mining region within a politically stable country serve to highlight to value of this giant deposit, making it attractive to all medium to large scale producers who desire a stable, low risk metal production stream. A key component of the PFS is the inclusion of high tonnage IPCC systems for the movement of waste rock. This achieves greater efficiencies in the movement of the pit overburden, not only to address rising operating costs for mining waste, but also the capital and operating costs involved in the construction of tailings dam walls using conventional methods. The mine reserves and key mine production characteristics are:

The mine reserves and key mine production characteristics are:

The PFS has considered a conventional concentrator process route for the sulphide ore but includes a roaster to reduce arsenic levels in the final copper concentrate to commercially acceptable levels and also a flotation tailings leach process to maximise gold recovery from the sulphide ore. In parallel with the concentrator a valley fill heapleach will be operated to recover gold from the near surface heap leachable material which is extracted as part of the overall mine development and operation.

Currently The company is fast tracking

Ongoing metallurgical programs designed to improve metal recoveries which if successful would positively impact the project economics,

Detailed geotechnical studies to support the infrastructure placement

Hydrology and hydrogeological studies both at Caspiche and locations with potential to act as viable water sources for the operations

Environmental base line programs to support an eventual EIA
All of which is designed to feed into a full feasibility study for the oxide stand alone portion of the project and a timely update the prefeasibility study on the larger project which is expected to both improve the already robust economics and address critical project development areas.


Financial Summary and Study Highlights:

The project showed robust economics and strong leverage at current gold prices to generate significant revenue with a a pre-tax Net Present Value (5% discount), calculated from the time of commencement of the project, of US$ 2,800 million and average operating costs of US$ 606 per ounce gold equivalent1. The gold production cost drops to US$ 18 per ounce when copper and silver by-product credits are considered.


-- Posted Monday, 30 January 2012 | Digg This Article | Source: GoldSeek.com

comments powered by Disqus







 



Increase Text SizeDecrease Text SizeE-mail Link of Current PagePrinter Friendly PageReturn to GoldSeek.com

 news.goldseek.com >> Story

E-mail Page  | Print  | Disclaimer 


© 1995 - 2019



GoldSeek.com Supports Kiva.org

© GoldSeek.com, Gold Seek LLC

The content on this site is protected by U.S. and international copyright laws and is the property of GoldSeek.com and/or the providers of the content under license. By "content" we mean any information, mode of expression, or other materials and services found on GoldSeek.com. This includes editorials, news, our writings, graphics, and any and all other features found on the site. Please contact us for any further information.

Live GoldSeek Visitor Map | Disclaimer


Map

The views contained here may not represent the views of GoldSeek.com, Gold Seek LLC, its affiliates or advertisers. GoldSeek.com, Gold Seek LLC makes no representation, warranty or guarantee as to the accuracy or completeness of the information (including news, editorials, prices, statistics, analyses and the like) provided through its service. Any copying, reproduction and/or redistribution of any of the documents, data, content or materials contained on or within this website, without the express written consent of GoldSeek.com, Gold Seek LLC, is strictly prohibited. In no event shall GoldSeek.com, Gold Seek LLC or its affiliates be liable to any person for any decision made or action taken in reliance upon the information provided herein.